Appendix G: Table for Estimating Time Allocations (FTE)

General guidance: divide the number of hours worked per week by 40 hours to compute FTE.

Examples:

Days worked per weekHours worked per weekFTE
5 days per week40 hours per week1 FTE
4 days per week32 hours per week.8 FTE
3 days per week24 hours per week.6 FTE
2.5 days per week20 hours per week.5 FTE
1 day per week8 hours per week.2 FTE
.5 (one half) day per week4 hours per week.1 FTE
.25 day per week2 hours per week.05 FTE

Alternative: divide the number of hours worked in the year by 2080 to compute FTE.

Hours worked per week x number of weeksHours per yearFTE
40 hours per week x 52 weeks2080 hours per year1 FTE
20 hours per week x 52 weeks1040 hours per year.5 FTE
10 hours per week x 12 weeks (summer)120 hours per year.06 FTE
40 hours per week x 32 weeks1,200 hours per year.62 FTE
40 hours per week x 1 week (one-week project)40 hours per year.02 FTE